A dairy that receives more than 200 tonnes of milk a day, averaged over the year, falls in class 7.2.1 of the EPA Act’s First Schedule and needs an EPA licence.

Last updated by Verdé Environmental Group

Key takeaways

  • Dairies receiving over 200 tonnes of milk a day need an EPA licence.
  • Breweries need one above 25 million litres a year; distilleries above 1,500 tonnes of pure alcohol.
  • Effluent to the sewer needs an Uisce Éireann licence; to a river, a Section 4 licence.
  • Abstracting 25 m³ of water on any day means registering it with the EPA.
Cutaway of a food and drink plant showing process water use, effluent treatment and discharge monitoring.
Cutaway of a food and drink production plant: process water use, effluent treatment and the point where the discharge is monitored.

What environmental support does a food or drink producer need?

Mostly four things: whether the plant needs an EPA licence at its size, a licence for its effluent, registration or a licence for the water it takes, and evidence when a neighbour complains about odour or noise. We cover all four, and investigate when process water gets where it should not.

Verdé supports Ireland’s food, dairy and distilling operators with IE licensing, trade effluent and discharge licences, water resource assessment and environmental due diligence.

Typical challenges we solve

  • IE and IPC licence applications and reviews
  • Trade effluent and discharge licence applications
  • Water abstraction licensing and resource assessment
  • Odour, noise and air-quality assessment

This page is for dairies, breweries, distilleries, meat plants and other food and drink producers in Ireland. It covers environmental licensing, effluent, water and nuisance, not food safety or HACCP.

Is this right for you?

This is a fit if

  • You run a dairy, brewery, distillery, meat plant or food factory near a class 7 threshold.
  • You need a trade effluent or Section 4 discharge licence.
  • You need to register or license a water abstraction.
  • A neighbour, the council or the EPA has raised odour or noise.

This is not a fit if

  • You need food safety, HACCP or labelling advice.
  • You need process or refrigeration engineering.

For food safety, start with the Food Safety Authority of Ireland. For the environmental side of the plant, we can help.

Does a dairy, brewery or distillery need an EPA licence?

It does above set capacities in class 7 of the First Schedule: for example, receiving more than 200 tonnes of milk a day, brewing more than 25 million litres a year, or distilling more than 1,500 tonnes of pure alcohol a year. The EPA decides each case.

Class 7 licence check

Choose what the site does and enter its capacity. Nothing is stored or sent.

What does the site do?

Choose what the site does, then enter its capacity.

How the class 7 check decides
EPA licence thresholds for food and drink activities
What you enterThresholdWhat it triggers
Milk received, average day over the yearmore than 200 t a dayclass 7.2.1
Dairy product capacity, as milk equivalentmore than 50 million gallons a yearclass 7.2.2
Production capacitymore than 25 million litres a yearclass 7.3.1
Production capacity, as pure alcoholmore than 1,500 t a yearclass 7.3.2
Production capacitymore than 100,000 t a yearclass 7.3.3
Carcass production capacitymore than 50 t a dayclass 7.4.1
Daily slaughter capacity, in unitsmore than 1,500 units a dayclass 7.4.2
Finished product capacitymore than 75 t a dayclass 7.8
Finished product capacitymore than 300 t a dayclass 7.8

Thresholds from class 7 of the First Schedule to the EPA Act 1992. The EPA decides each case.

Planning has its own thresholds. An EIA report is mandatory for dairy processing above 50 million gallons of milk equivalent a year, brewing and distilling above 100,000 tonnes a year, and slaughterhouses above 1,500 units a day (Schedule 5).

Who licenses a food plant’s wastewater?

It depends where the water goes. Trade effluent to the public sewer needs a licence from Uisce Éireann, which names food and drink among the sectors it licenses, or an EPA licence. Effluent to a river or stream needs a Section 4 licence from the local authority, unless an EPA licence covers it.

Where a food plant’s water comes from and goesFlow diagram: water in at 25 or 2,000 m³ a day, out to the sewer under Section 16 or to a river under Section 4.Food or drink plantprocess waterWater in25 m³ in any 24 hours:register with the EPA2,000 m³: EPA licencePublic sewerTrade effluent licenceUisce Éireann, Section 16River or streamSection 4 licencefrom the local authorityWhere the site holds an EPA licence, it can cover the discharges instead.
The licences that attach to water coming into and leaving a food or drink plant. An EPA licence, where the site holds one, can cover the discharges instead. Source: Uisce Éireann.
Data behind this graphic: water routes and their licences
RouteThreshold or ruleWho licenses itSource
Water in, from a well, river or lake25 m³ or more in any 24 hours: registerEPAEPA
Water in, from a well, river or lake2,000 m³ or more in any 24 hours: licenceEPAEPA
Effluent out, to the public sewerTrade effluent licence, Section 16Uisce Éireann, or the EPAUisce Éireann
Effluent out, to a river or streamSection 4 licenceLocal authority, or the EPADublin City Council

Uisce Éireann grants trade effluent licences under Section 16 of the Local Government (Water Pollution) Acts 1977 and 1990, and discharging trade effluent without one is an offence (Uisce Éireann). Section 4 licences for discharges to waters come under the same Acts (Dublin City Council). We prepare the applications (licensing).

Does a food or drink plant need to register its water abstraction?

If it takes 25 cubic metres or more in any 24 hours, yes: the abstraction is registered with the EPA, which then decides whether a licence is needed. From 2,000 cubic metres in any 24 hours a licence is required. The busiest day counts, not the average.

The thresholds are on the EPA’s abstraction page. We characterise the source, test its yield and prepare the registration or licence dossier (water and hydrogeology).

How are odour and noise complaints about a food plant assessed?

With measured evidence. Odour around a licensed site is assessed with the EPA’s AG5 field method, alongside olfactometry, community panels and dispersion modelling, and noise is surveyed at the nearest homes to the EPA’s NG4 guidance. The results show whether the plant is the source, and by how much.

The methods are in the EPA’s AG5 odour guidance and NG4 noise guidance. Our air, noise and acoustics page covers which applies to a planning condition, a licence or a complaint.

What happens if process water reaches land or a stream?

Contain it first, then find out what it reached. A Phase II site assessment samples the soil and the stream, compares the results with assessment criteria and builds a conceptual site model of source, pathway and receptor. We carried one out after a discharge of process wash water to nearby land.

If a river or stream is affected, report it: our contaminated land page sets out how the investigation and any clean-up proceed.

What changes the job at a food or drink plant?

Size first, then water: the plant’s capacity decides whether class 7 applies, and where its water comes from and goes to decides which other licences it needs. A complaint or an incident adds evidence on top.

If this is true of your plant

  • If a dairy receives more than 200 tonnes of milk a day, averaged over the year

    then it falls in class 7.2.1 and needs an EPA licence.

  • If process effluent goes to the public sewer

    then it needs a trade effluent licence from Uisce Éireann, or an EPA licence.

  • If effluent goes to a river or stream

    then it needs a Section 4 licence from the local authority, unless an EPA licence covers it.

  • If the plant abstracts 25 m³ of water or more on any day

    then the abstraction must be registered with the EPA; at 2,000 m³ it needs a licence.

How Verdé compares on what food and drink producers weigh up
CriterionVerdéWhat it means for you
LicensingEPA licence, trade effluent and Section 4 applicationsEvery authorisation for the site from one team.
WaterAbstraction registration and licence dossiersThe busiest day measured, not guessed.
Odour and noiseAG5 odour assessment and NG4 noise surveysEvidence that settles a complaint either way.
IncidentsPhase II site assessment after a dischargeSoil and stream results with a conceptual site model.
Staffed officesKilcoole, Castlebar and CorkTeams in the east, west and south.

Food and drink questions we are asked most

Still have a question? Call 01 201 1260 or email info@verde.ie.

Does a dairy or distillery in Ireland need an EPA licence?

Above set capacities, yes. A dairy receiving more than 200 tonnes of milk a day, averaged over the year, falls in class 7.2.1 of the First Schedule, and dairy product capacity above 50 million gallons of milk equivalent a year in class 7.2.2. A distillery needs one above 1,500 tonnes of pure alcohol a year. The EPA decides each case.

What are the EPA licence thresholds for breweries and maltings?

Brewing, including cider and perry, falls in class 7.3.1 of the First Schedule above a production capacity of 25 million litres a year. Malting falls in class 7.3.3 above 100,000 tonnes a year. Activities in the schedule need an EPA licence. Below those sizes, trade effluent, discharge and water abstraction rules can still apply to the site.

Does a slaughterhouse need an EPA licence?

It does above either of two thresholds. Class 7.4.1 covers slaughterhouses with a carcass production capacity above 50 tonnes a day. Class 7.4.2 covers slaughter above 1,500 units a day, where one sheep counts as 1 unit, one pig as 2 and one head of cattle as 5. At planning stage, more than 1,500 units a day also means a mandatory EIA report.

Who licenses wastewater from a food plant?

Uisce Éireann licenses trade effluent going to its sewers, and names food and drink among the sectors that need one; an EPA licence can cover it instead. A discharge to a river or stream is licensed by the local authority under Section 4, again unless the EPA licence covers it. Discharging trade effluent without a licence is an offence. Verdé prepares the applications.

Does a food plant need to register its water abstraction?

Yes, if it takes 25 cubic metres or more in any 24 hours. The abstraction is registered with the EPA, which then decides whether a licence is needed. From 2,000 cubic metres in any 24 hours a licence is required. The busiest day counts, so a seasonal plant can cross the threshold even with a low average.

How is an odour complaint about a food plant assessed?

With measurements, not impressions. Around a licensed site, odour is assessed with the EPA’s AG5 field method, alongside olfactometry, community panels and dispersion modelling, which together show how far odour travels and how strong it is at nearby homes. Noise complaints are surveyed at the nearest homes to the EPA’s NG4 guidance. Verdé carries out both.

Does a new dairy or brewery need an EIA report?

An EIA report is mandatory for dairy processing above 50 million gallons of milk equivalent a year, and for brewing and distilling above 100,000 tonnes a year, under Schedule 5 of the Planning and Development Regulations. Smaller plants are screened to decide whether one is needed. Verdé prepares EIAR chapters on water, soils and noise.

Terms used on this page

Milk equivalent
Milk equivalent expresses a dairy product as the quantity of milk used to make it.
Slaughter units
Units weight slaughter capacity by animal: one sheep is 1 unit, one pig 2 and one head of cattle 5.
Trade effluent
Trade effluent is any liquid waste discharged from a business premises to the public sewers.
Section 4 licence
A Section 4 licence, from the local authority, allows a discharge of effluent to waters such as a river.
Olfactometry
Olfactometry measures odour concentration by diluting air samples for a trained panel.

Sources and further reading

  1. First Schedule to the EPA Act 1992, as amendedEnvironmental Protection Agency, checked 3 November 2026. The activity classes and capacity thresholds that bring a site under an EPA licence.
  2. Current EIA screening thresholds (Schedule 5, Part 2)Department of Housing, Local Government and Heritage, checked 3 November 2026. The project sizes above which an EIA report is mandatory, for applications lodged up to 25 November 2026.
  3. About trade effluentUisce Éireann, checked 3 November 2026. Who needs a trade effluent licence to discharge to the public sewer.
  4. Discharge licencesDublin City Council, checked 3 November 2026. Section 4 licences for discharges to waters and Section 16 licences for discharges to sewer.
  5. Do I need to register or apply for a licence?Environmental Protection Agency, checked 3 November 2026. The 25 and 2,000 cubic metre a day water abstraction thresholds.
  6. Odour Impact Assessment Guidance for EPA Licensed Sites (AG5)Environmental Protection Agency, 2021 edition. The field method for assessing odour around licensed sites.
  7. Guidance Note for Noise: licence applications, surveys and assessments (NG4)Environmental Protection Agency, 2016. The noise survey and assessment method for licensed sites.

Read this page in Markdown

Tell us about the plant

What we ask for

  • The site address
  • What the plant makes, and its capacity
  • Your licence or discharge permit details, if any
  • Recent monitoring results
  • Any issue raised by the EPA, the council or a neighbour

Reply

Within one working day.

For a spill or pollution incident, phone 0818 714 002 at any hour. The duty engineer confirms the response on the call.