Sector
Renewable energy planning evidence for wind and solar projects
From 26 November 2026, a wind farm needs an EIA report once it has more than 5 turbines, whatever its output, under the 2026 screening regulations. Applications lodged up to 25 November also count a total output above 5 megawatts.
Last updated by Verdé Environmental Group
Key takeaways
- From 26 November 2026, a wind farm with more than 5 turbines needs an EIA report, whatever its output.
- The 5 MW output test applies only to applications lodged up to 25 November 2026.
- Overhead power lines of 200 kV or more need an EIA report under both sets of rules.
- Solar farms are not a listed class for EIA, so a solar farm on its own does not usually need one.
- We design and install solar PV: 94 kWp across two Dublin roofs in 2025.

What environmental work does a renewable energy project need?
Three stages, three kinds of evidence: at planning, the EIA thresholds, screening and Appropriate Assessment; during construction, water, soil, waste and noise controls; and for rooftop solar, the design and installation itself. We cover the evidence at every stage and install the solar.
Verdé supports Irish renewable energy projects through feasibility, EIAR and Appropriate Assessment, planning, construction environmental management and monitoring, and designs and installs solar PV.
Typical challenges we solve
- EIAR and Appropriate Assessment for wind and solar projects
- Construction environmental management and water monitoring
- Soil classification and materials management on site
- Solar PV design and installation
This page is for developers, landowners and contractors on wind and solar projects in Ireland, and for businesses adding rooftop solar PV. It covers environmental assessment, construction monitoring and solar installation, not turbine supply or energy trading.
Is this right for you?
This is a fit if
- You are planning a wind or solar project and need to know whether it needs an EIA report.
- You need Appropriate Assessment screening or a Natura Impact Statement.
- You are building and need water monitoring, soil classification or a materials management plan.
- You want rooftop solar PV designed and installed.
This is not a fit if
- You need turbines, panels or inverters supplied on their own.
- You need a power purchase agreement or energy trading advice.
For equipment supply and energy contracts, a developer or supplier leads. We provide the environmental evidence and, for rooftop solar, the installation.
When does a wind farm need an EIA report?
For applications lodged from 26 November 2026, when it has more than 5 turbines, whatever their output. From 2 to 5 turbines the project is screened, and a single turbine gets an examination only. Applications lodged up to 25 November 2026 also needed an EIA report above 5 megawatts of total output.
Wind farm EIA check
Choose when the application will be lodged, then enter the turbine count or a grid line voltage. Nothing is stored or sent.
More than 5 turbines needs an EIA report. Fewer than 2 gets an examination only. Output no longer counts.
An overhead line of 200 kV or more needs an EIA report. 110 kV or less gets an examination only.
Choose when the application will be lodged, then enter the turbine count or a grid line voltage.
How the EIA check decides
| What you enter | EIA report: lodged from 26 Nov 2026 | Examination only: lodged from 26 Nov 2026 | EIA report: lodged up to 25 Nov 2026 |
|---|---|---|---|
| Number of turbines | more than 5 turbines | less than 2 turbines | more than 5 turbines |
| Total output of the wind farm | Not counted | Not counted | more than 5 MW |
| Overhead grid line voltage, if any | at least 200 kV | at most 110 kV | at least 200 kV |
Thresholds from Schedule 2 of the 2026 screening regulations, class 3(h) for wind farms and 3(b) for overhead lines, and for applications lodged up to 25 November 2026 from Schedule 5, Part 2 of the 2001 Regulations, classes 3(i) and 3(b). The planning authority decides.
The 2026 regulations replaced Schedule 5 for applications lodged from 26 November 2026. For wind farms they dropped the 5 megawatt output test, kept the threshold of more than 5 turbines and added a lower band: below 2 turbines, the planning authority examines only the nature and location of the project. Our EIA threshold check covers other kinds of project.
Lodged up to 25 November 2026
More than 5 turbines or more than 5 MW
Lodged from 26 November 2026
More than 5 turbines, whatever the output
- A
- 6 turbines, 4.8 MW
- B
- 3 turbines, 6 MW
- C
- 4 turbines, 4 MW
- D
- 1 turbine, 3 MW
| Example | Turbines | Total output | Lodged up to 25 Nov 2026 | Lodged from 26 Nov 2026 |
|---|---|---|---|---|
| A | 6 turbines of 0.8 MW | 4.8 MW | EIA report mandatory: more than 5 turbines | EIA report mandatory: more than 5 turbines |
| B | 3 turbines of 2 MW | 6 MW | EIA report mandatory: more than 5 MW | Screened: output no longer counts |
| C | 4 turbines of 1 MW | 4 MW | Screened: below both thresholds | Screened: 2 to 5 turbines |
| D | 1 turbine of 3 MW | 3 MW | Screened: below both thresholds | Examination only: fewer than 2 turbines |
Does a solar farm need an EIA report?
Not usually on its own. Solar farms are not a listed class in the 2001 Schedule 5 or the 2026 regulations, and two 2020 High Court judgments found solar farms of the kind at issue fall outside the listed classes. A part that is in a class, such as a 200 kV overhead line, is tested on its own.
The Minister for Housing set this out in a written Dáil answer on 11 May 2022, citing Sweetman v An Bord Pleanála [2020] IEHC 39 and Kavanagh v An Bord Pleanála [2020] IEHC 259, and added that a solar farm could still need EIA where one of its parts falls within a listed class (Oireachtas). The planning authority, or An Coimisiún Pleanála, decides each application.
Appropriate Assessment is a separate test that applies whatever the type of project, so a solar farm near a Natura 2000 site still needs Appropriate Assessment screening. We prepare EIA screening reports, Appropriate Assessment screening and, where one is needed, the EIAR chapters (environmental consultancy).
When does a wind or solar project need an Appropriate Assessment?
When it could affect a Natura 2000 site, meaning a Special Area of Conservation or a Special Protection Area, and significant effects cannot be ruled out at screening. Screening checks every European site the project could affect, including sites downstream along a river.
SACs are designated under the EU Habitats Directive (NPWS). Where screening cannot rule out significant effects, we prepare the Natura Impact Statement that the planning authority relies on (appropriate assessments).
What environmental controls does a wind or solar build need?
Water protection, soil and waste management, and noise and dust control, usually set out in the planning conditions. We monitor surface water and groundwater during construction, classify excavated soil, prepare the materials management plan and survey noise at the nearest homes.
Under the EPA’s 2021 guidelines, energy infrastructure projects fall in Tier 2 for their Resource and Waste Management Plan. Our waste management page covers soil classification and the paperwork for every load, and our hydrogeology page covers water monitoring.
Can Verdé design and install solar PV?
Yes. We design and install rooftop solar PV for homes and businesses, from a 6.2 kWp system on a slate roof in Castlebar to a 94 kWp system across two Dublin city centre roofs 35 metres up, installed in 2025 with a scheduled crane lift.
2025
94 kWp solar PV on two city centre roofs
Dublin
- Two roofs 35 metres up, with materials lifted by a scheduled crane
- 440 W modules, dual hybrid inverters and linear heat detection
2025
Commercial solar PV
Co. Wicklow
- A 10.44 kWp system designed and installed for a commercial premises
2024
Residential solar PV
Castlebar, Co. Mayo
- A 6.2 kWp system designed for a slate roof
Verde Remediation Services Ltd, part of Verdé Environmental Group, is on SEAI’s list of registered solar PV companies, registration 50338, for homes and businesses in every county (SEAI). In 2023 Verdé Solar took a stand at the National Ploughing Championships to meet farm and home owners (Verdé news). Our solar PV page has more on design and installation.
What changes the job on a renewable energy project?
Mostly size, timing and setting: the number of turbines, the date the application is lodged, any overhead grid line, how close the site is to a Natura 2000 site, and what the planning conditions ask for during construction. Each one changes which reports the project needs.
If this is true of your project
If a wind farm lodged from 26 November 2026 has more than 5 turbines
then an EIA report is mandatory with the planning application, whatever the output.
If a wind farm lodged from 26 November 2026 has 2 to 5 turbines
then it is screened for EIA; a single turbine gets an examination of nature and location only.
If the application was lodged up to 25 November 2026
then a total output above 5 MW also made an EIA report mandatory.
If an overhead power line is 200 kV or more
then it needs an EIA report too, under both sets of rules.
If the project could affect a Natura 2000 site
then it needs Appropriate Assessment screening, and a Natura Impact Statement where effects cannot be ruled out.
If the project is energy infrastructure
then the EPA’s 2021 guidelines put it in Tier 2 for its Resource and Waste Management Plan.
| Criterion | Verdé | What it means for you |
|---|---|---|
| Planning | EIAR chapters, screening reports and Natura Impact Statements | The environmental case for the application from one team. |
| Construction | Water monitoring, soil classification and materials management | Evidence that the build is not harming nearby water. |
| Solar PV | Design and installation, from 6.2 kWp to 94 kWp, as an SEAI-registered solar PV company | We install as well as assess. |
| Noise | Surveys and assessments at the nearest homes | Evidence for planning conditions. |
| Staffed offices | Kilcoole, Castlebar and Cork | Teams in the east, west and south. |
Renewable energy questions we are asked most
Still have a question? Call 01 201 1260 or email info@verde.ie.
When does a wind farm in Ireland need an EIA report?
For applications lodged from 26 November 2026, when it has more than 5 turbines, under class 3(h) of Schedule 2 to the 2026 screening regulations; output no longer counts. From 2 to 5 turbines the project is screened, and a single turbine gets an examination only. Applications lodged up to 25 November 2026 also needed an EIA report above 5 megawatts. Verdé prepares EIAR chapters and screening reports.
What changed for wind farms on 26 November 2026?
The Planning and Development (Part 6) (Screening Classes, Thresholds, Criteria and Examination) Regulations 2026 replaced Schedule 5 of the 2001 Regulations for applications lodged from that date. For wind farms they dropped the 5 megawatt output test, kept the threshold of more than 5 turbines, and added a lower band: a wind farm of fewer than 2 turbines gets an examination of its nature and location only.
Does a solar farm need an EIA report?
Not usually on its own. Solar farms are not a listed class in Schedule 5 of the 2001 Regulations or in the 2026 screening regulations, and two High Court judgments in 2020 found solar farms of the kind at issue fall outside the listed classes. A solar farm can still need EIA where one of its parts falls within a class, and the planning authority decides. Appropriate Assessment is a separate test.
Does a grid line need an EIA report?
An overhead power line of 200 kilovolts or more needs an EIA report, under class 3(b) in both the 2001 and the 2026 rules. For applications lodged from 26 November 2026, a line of 110 kilovolts or less gets an examination of its nature and location only, and lines in between are screened. Appropriate Assessment applies separately wherever a route could affect a Natura 2000 site.
When does a renewable project need an Appropriate Assessment?
Whenever a wind farm, solar farm or grid route could affect a Special Area of Conservation or a Special Protection Area. Screening comes first and checks every European site within reach, including sites downstream along a river. Where significant effects cannot be ruled out, we prepare the Natura Impact Statement, and the planning authority makes its decision on it.
Can Verdé monitor water quality during construction?
Yes. We monitor surface water and groundwater so you can show that construction is not harming nearby water, sampling to the programme the planning conditions set and reporting the results. On the same sites we classify excavated soil, prepare the materials management plan and survey noise at the nearest homes, so one team covers the conditions.
Does Verdé install solar PV?
Yes. Verdé designs and installs rooftop solar PV for homes and businesses, and is on SEAI’s list of registered solar PV companies (registration 50338). Recent systems include 6.2 kWp on a slate roof in Castlebar in 2024, 10.44 kWp for a commercial premises in Wicklow in 2025, and 94 kWp across two Dublin city centre roofs 35 metres up in 2025, with a scheduled crane lift.
What waste plan does a renewable energy project need?
Under the EPA’s 2021 guidelines for construction and demolition projects, energy infrastructure falls in Tier 2, which means a full Resource and Waste Management Plan rather than the simplified template. Excavated soil is sampled and classified before it moves, so it can be reused or sent to a suitably authorised destination. Verdé prepares the plan and the classification.
Terms used on this page
- EIA screening
- EIA screening decides whether a project below a mandatory threshold still needs an EIA report.
- Examination
- Examination is the lighter check for the smallest projects from 26 November 2026: the authority looks at nature and location only.
- Total output
- Total output is the combined rated capacity of all turbines on a wind farm, in megawatts. It counts only for applications lodged up to 25 November 2026.
- kWp
- kWp, kilowatt peak, is a solar PV system’s output under standard test conditions.
- Natura Impact Statement
- A Natura Impact Statement is the report prepared when screening cannot rule out effects on a Natura 2000 site.
- Resource and Waste Management Plan
- A Resource and Waste Management Plan sets out how a project will prevent, reuse and manage construction waste.
Sources and further reading
- Planning and Development (Part 6) (Screening Classes, Thresholds, Criteria and Examination) Regulations 2026Department of Housing, Local Government and Heritage, checked 24 November 2026. The EIA thresholds for applications lodged from 26 November 2026.
- Current EIA screening thresholds (Schedule 5, Part 2)Department of Housing, Local Government and Heritage, checked 3 November 2026. The project sizes above which an EIA report is mandatory, for applications lodged up to 25 November 2026.
- Solar farms and environmental impact assessment: written answer, Question 116Houses of the Oireachtas, 2022. Solar farms are not a listed EIA class, citing Sweetman [2020] IEHC 39 and Kavanagh [2020] IEHC 259.
- Solar PV companiesSustainable Energy Authority of Ireland, checked 26 November 2026. Verde Remediation Services Ltd is a registered solar PV company, registration 50338, for homes and businesses in every county.
- Special Areas of ConservationNational Parks and Wildlife Service, checked 3 November 2026. What SACs are and how Natura 2000 sites are designated.
- Best practice guidelines for resource and waste management plans for construction and demolition projectsEnvironmental Protection Agency, 2021. The Tier 1 and Tier 2 thresholds and who prepares the plan.
Tell us about the project
What we ask for
- The project location and site boundary
- The technology and size, such as turbines and total output
- The planning stage, the date you plan to lodge and your submission deadline
- Any protected sites you already know are nearby
- For rooftop solar, the building address and roof type
Reply
Within one working day.
For a spill or pollution incident, phone 0818 714 002 at any hour. The duty engineer confirms the response on the call.
Office 01 201 1260 or info@verde.ie
Related pages
- Solar PVRooftop solar design and installation.
- Appropriate assessmentsScreening and Natura Impact Statements.
- Environmental consultancyEIAR chapters and planning support.
- Waste managementSoil classification and materials management.
- Hydrogeology and groundwaterWater monitoring during construction.
- Energy & Electricity InfrastructurePlanning and monitoring for grid projects.