# Data centres water, power and planning evidence for campus projects

Combustion plant, backup generators included, with a total rated thermal input of 50 MW or more falls in class 2.1 of the EPA Act’s [First Schedule](https://www.epa.ie/publications/licensing--permitting/industrial/ipc/First-Schedule-of-EPA-Act-1992-as-amended---V5-Peat-Regs-updates.pdf) and needs an EPA licence.

Last updated 3 November 2026 by Verdé Environmental Group

## Key takeaways

- Generator plant of 50 MW thermal input or more needs an EPA licence under class 2.1.
- Abstracting 25 m³ of water a day means registering with the EPA; 2,000 m³ means a licence.
- Industrial estate developments over 15 hectares need an EIA report at planning stage.
- In 2025 we managed water control on the first two phases of the DUB1 campus at Profile Park.

Cutaway of a data centre campus: cooling plant, backup generators, bunded fuel storage and the surface water drainage below.

## What environmental evidence does a data centre project need?

Four questions come up on most campuses: whether the water supply must be registered or licensed, whether the generator plant needs an EPA licence, what the planning application must assess, and how groundwater is controlled during construction. We answer each one with measured data.

Data centres demand water, power and rigorous environmental consenting. Verdé delivers groundwater assessments, abstraction registration and licensing, planning-stage environmental input and construction dewatering for data centre developers.

### Typical challenges we solve

- Groundwater resource and abstraction assessment
- EIAR, AA and planning-stage environmental input
- Construction dewatering and water control
- Noise, air quality and construction environmental management

This page is for developers, contractors and operators of data centres and other technology campuses in Ireland. It covers environmental consents, assessment and monitoring, not building design or grid connection agreements.

### Services in this sector

- [Water & Hydrogeology](https://verde.ie/services/water-hydrogeology)
- [Construction Dewatering](https://verde.ie/services/construction-dewatering)
- [Appropriate Assessments](https://verde.ie/services/appropriate-assessments)
- [Air, Noise & Acoustics](https://verde.ie/services/air-noise-acoustics)

### Response times

New enquiries: a reply within one working day. Spills and pollution incidents: call [0818 714 002](tel:0818714002) at any hour, and the duty engineer confirms the response on the call.

## Is this right for you?

### This is a fit if

- You are planning a data centre and need to know which consents the water, power and site will trigger.
- You need groundwater assessment or an abstraction registration or licence.
- You need noise or air assessment for generator plant.
- You are building and need dewatering designed, licensed and monitored.

### This is not a fit if

- You need data hall, cooling or electrical design.
- You need a grid connection offer or energy trading advice.

For building and electrical design, your design team leads. We provide the environmental evidence their design has to satisfy.

## Which consents will a data centre campus trigger?

It depends on five numbers and facts: the water you abstract, the thermal input of your combustion plant, the site area, where process or cooling water goes, and whether a Natura 2000 site is nearby. The check below tests each one against the official threshold.

**How the campus consent check decides**

Table: What the campus consent check tests

| What you enter | Threshold | What it triggers |
| --- | --- | --- |
| Water abstraction | 25 m³ or more in any 24 hours | Registration with the EPA, which assesses whether a licence is needed |
| Water abstraction | 2,000 m³ or more in any 24 hours | An EPA abstraction licence |
| Combustion plant, including generators | 50 MW or more total rated thermal input | An EPA licence under class 2.1 |
| Site area | Industrial estate development over 15 hectares | A mandatory EIA report |
| Discharge route | Trade effluent to the public sewer | A trade effluent licence from Uisce Éireann, or an EPA licence |
| Discharge route | Trade effluent to a river, stream or groundwater | A Section 4 licence from the local authority, or an EPA licence |
| Protected sites | A Natura 2000 site nearby | Appropriate Assessment, starting with screening |

Thresholds from the [First Schedule](https://www.epa.ie/publications/licensing--permitting/industrial/ipc/First-Schedule-of-EPA-Act-1992-as-amended---V5-Peat-Regs-updates.pdf), the [EPA abstraction rules](https://www.epa.ie/our-services/licensing/freshwater--marine/water-abstraction/do-i-need-to-register-or-apply-for-a-licence/), the [Schedule 5 EIA thresholds](https://consult.housing.gov.ie/en/system/files/materials/8/Current%20Environmental%20Impact%20Assessment%20Screening%20Thresholds.pdf) and [Uisce Éireann](https://water.ie/business/trade-effluent/about). The EPA, the planning authority and Uisce Éireann make the decisions.

**Figure: Consent thresholds across a data centre campus.** Strip graphic: water 25 and 2,000 m³ a day, generators 50 MW, site 15 ha, discharges to sewer or river, a Natura site.

Each consent a campus can trigger, in the order water and energy pass through the site. The thresholds are the official ones; the EPA, the planning authority and Uisce Éireann decide each case. Source: [EPA First Schedule](https://www.epa.ie/publications/licensing--permitting/industrial/ipc/First-Schedule-of-EPA-Act-1992-as-amended---V5-Peat-Regs-updates.pdf).

Table: Data behind this graphic: thresholds on a data centre campus

| Part of the campus | Threshold | What it triggers | Source |
| --- | --- | --- | --- |
| Site area | Industrial estate development over 15 hectares | EIA report mandatory | Schedule 5 |
| Generators and other combustion plant | 50 MW or more total rated thermal input | EPA licence, class 2.1 | EPA First Schedule |
| Water supply | 25 m³ or more in any 24 hours | Registration with the EPA | EPA |
| Water supply | 2,000 m³ or more in any 24 hours | EPA abstraction licence | EPA |
| Groundwater supply | More than 2 million m³ a year | EIA report mandatory | Schedule 5 |
| Discharge to sewer | Trade effluent | Trade effluent licence | Uisce Éireann |
| Discharge to a river | Trade effluent | Section 4 licence | Local authority |
| Nearby protected site | Effects cannot be ruled out | Appropriate Assessment | Planning authority |

## Does a data centre need to register or license its water abstraction?

Yes, above set volumes. Abstracting 25 cubic metres or more in any 24 hours must be registered with the EPA, which then assesses whether a licence is needed; at 2,000 cubic metres or more a licence is required. Groundwater abstraction above 2 million cubic metres a year also needs an EIA report.

The volumes are the most water taken in any 24-hour period, not the average ([EPA](https://www.epa.ie/our-services/licensing/freshwater--marine/water-abstraction/do-i-need-to-register-or-apply-for-a-licence/)). We assess the groundwater resource, run the yield tests and prepare the registration or licence dossier ([water and hydrogeology](https://verde.ie/services/water-hydrogeology)).

## When do data centre generators need an EPA licence?

When the combustion plant on site has a total rated thermal input of 50 MW or more. That is class 2.1 of the First Schedule to the EPA Act, and activities in that schedule need an EPA licence. Thermal input measures the fuel burned, so it is higher than the electrical output of the same generators.

For the licence and the planning application, we model generator emissions with AERMOD and ADMS to the EPA’s [AG4 guidance](https://www.epa.ie/publications/compliance--enforcement/air/air-guidance-notes/epa-air-dispersion-modelling-guidance-note-ag4-2020.php), and survey and assess noise at the nearest homes to the EPA’s [NG4 method](https://www.epa.ie/publications/monitoring--assessment/noise/guidance-note-for-noise-licence-applications-surveys-and-assessments-in-relation-to-scheduled-activities-ng4.php).

Our [air, noise and acoustics](https://verde.ie/services/air-noise-acoustics) page covers the methods and when each applies.

## What does a data centre planning application need to assess?

Usually water supply and groundwater, noise, air quality, and effects on any nearby Natura 2000 site. An EIA report is mandatory for industrial estate developments over 15 hectares, and smaller projects are screened. An Appropriate Assessment is needed where significant effects on a European site cannot be ruled out.

The thresholds are in [Schedule 5](https://consult.housing.gov.ie/en/system/files/materials/8/Current%20Environmental%20Impact%20Assessment%20Screening%20Thresholds.pdf) of the Planning and Development Regulations. We prepare EIAR chapters and Appropriate Assessment screening reports and Natura Impact Statements ([appropriate assessments](https://verde.ie/services/appropriate-assessments)).

## How is groundwater controlled while a data centre is built?

By dewatering: pumping groundwater out of excavations below the water table, treating it and discharging it under a licence, with monitoring throughout. At Profile Park in 2025 we managed water control on the first two phases of the DUB1 campus, from planning and licensing to installation and compliance monitoring.

- **2025**: [Construction dewatering, Profile Park DUB1 campus](https://verde.ie/projects/construction-dewatering-profile-park) Profile Park, Dublin, for John Sisk & Son Ltd First two phases of Vantage Data Centers’ 22-acre DUB1 campus; 52 MW of IT capacity across two facilities, of 32 MW and 20 MW; Water control from planning and licensing to system installation and compliance monitoring

Pumped water to the foul sewer needs a trade effluent licence ([Uisce Éireann](https://water.ie/business/trade-effluent/about)), and water to a river or stream needs a Section 4 licence from the local authority ([Dublin City Council](https://www.dublincity.ie/environment-and-climate-action/protecting-against-water-pollution/discharge-licences)). Our [construction dewatering](https://verde.ie/services/construction-dewatering) page sets out the design and monitoring.

## What happens if diesel leaks at a data centre?

Stop the source if it is safe to do so, keep the fuel out of drains, and call 0818 714 002 at any hour. Our team helps contain the spill, clean up and report on the site afterwards, with sampling to show the result.

If fuel reaches a river or stream, Inland Fisheries Ireland’s 24-hour line takes reports of water pollution on 0818 34 74 24 ([IFI](https://fisheriesireland.ie/contact-us)). The clean-up stages are on our [oil spill clean-up](https://verde.ie/oil-spill-clean-up) page.

## What changes the job on a data centre campus?

Mainly scale and setting: how much water and fuel the campus uses, how large the site is, where water leaves it, and what lies downstream. Those decide which consents apply, which in turn decides the evidence each consent needs.

### If this is true of your campus

- **If the combustion plant on site, generators included, has a total rated thermal input of 50 MW or more**: then the site falls in class 2.1 of the First Schedule and needs an EPA licence.
- **If the site abstracts 25 m³ of water or more in any 24 hours**: then the abstraction must be registered with the EPA; at 2,000 m³ it needs a licence.
- **If the development is an industrial estate of more than 15 hectares**: then an EIA report is mandatory with the planning application.
- **If diesel reaches a drain or watercourse**: then call 0818 714 002, and Inland Fisheries Ireland on 0818 34 74 24 if a river or stream is affected.

Table: How Verdé compares on what data centre teams weigh up

| Criterion | Verdé | What it means for you |
| --- | --- | --- |
| Water | Groundwater assessment and abstraction dossiers | Registration or licence evidence from one team. |
| Construction | Dewatering design, licensing and monitoring | As delivered on the Profile Park DUB1 campus. |
| Air and noise | AERMOD and ADMS modelling, NG4 noise surveys | Generator emissions and noise assessed to EPA guidance. |
| Spills | 24-hour line, 0818 714 002 | Someone answers at any hour, including weekends. |
| Staffed offices | Kilcoole, Castlebar and Cork | Teams in the east, west and south. |

## Data centre questions we are asked most

Still have a question? Call [01 201 1260](tel:+35312011260) or email [info@verde.ie](mailto:info@verde.ie).

### Does a data centre need an EPA licence for its generators?

It does once the combustion plant on site, backup generators included, has a total rated thermal input of 50 MW or more. That is class 2.1 of the First Schedule to the EPA Act, and activities in that schedule need an EPA licence. Thermal input is the fuel burned, so it is higher than the generators’ electrical output. The EPA decides each case.

### When does a data centre need to register its water abstraction?

When it takes 25 cubic metres of water or more in any 24-hour period. Registration goes to the EPA, which then assesses whether a licence is needed for abstractions up to 1,999 cubic metres a day. At 2,000 cubic metres or more in any 24 hours, a licence is required. Verdé assesses the resource and prepares the dossier.

### Does a data centre project need an EIA report?

An EIA report is mandatory when a project passes a Schedule 5 threshold, such as an industrial estate development over 15 hectares or groundwater abstraction above 2 million cubic metres a year. Smaller projects are screened to decide whether one is needed. Verdé prepares EIAR chapters on water, soils and noise, and Appropriate Assessment where a Natura 2000 site could be affected.

### Can Verdé assess noise from data centre generators?

Yes. We carry out noise surveys and assessments to support planning and to check compliance with conditions, measuring at the nearest homes and following the EPA’s NG4 guidance where the site is licensed. For generator exhaust, we model air dispersion with AERMOD and ADMS to the EPA’s AG4 guidance, so both noise and emissions are covered in one assessment.

### What happens if diesel leaks at a data centre?

Stop the source if it is safe, keep the fuel out of drains and call Verdé’s 24-hour line on 0818 714 002. Our team helps contain the spill, clean up and report on the site afterwards, with sampling to show the result. If the fuel reaches a river or stream, also call Inland Fisheries Ireland on 0818 34 74 24.

### What did Verdé do at Profile Park?

In 2025 Verdé supported John Sisk & Son Ltd on the first two phases of Vantage Data Centers’ DUB1 campus at Profile Park, Dublin: 22 acres and 52 MW of IT capacity across two facilities. We managed water control, from strategic planning and regulatory licensing to installing the dewatering system and monitoring compliance.

### Who licenses water discharged from a data centre site?

It depends where the water goes. Trade effluent to the public sewer needs a licence from Uisce Éireann, granted under Section 16 of the Local Government (Water Pollution) Acts, or an EPA licence. Trade effluent to a river or stream needs a Section 4 licence from the local authority, unless an EPA licence covers it.

## Terms used on this page

- **Rated thermal input**: Rated thermal input is the rate at which a combustion plant burns fuel, in MW. Class 2.1 starts at 50 MW.
- **Abstraction**: Abstraction is taking water from a river, lake or the ground. The EPA registers or licenses it above set daily volumes.
- **Dewatering**: Dewatering is pumping groundwater out of an excavation so work can continue below the water table.
- **EIA report**: An EIA report sets out a project’s likely significant effects on the environment, for the planning decision.
- **Section 4 licence**: A Section 4 licence, from the local authority, allows a discharge of trade effluent to waters such as a river.

## Sources and further reading

1. [First Schedule to the EPA Act 1992, as amended](https://www.epa.ie/publications/licensing--permitting/industrial/ipc/First-Schedule-of-EPA-Act-1992-as-amended---V5-Peat-Regs-updates.pdf)Environmental Protection Agency, checked 3 November 2026. The activity classes and capacity thresholds that bring a site under an EPA licence.
2. [Do I need to register or apply for a licence?](https://www.epa.ie/our-services/licensing/freshwater--marine/water-abstraction/do-i-need-to-register-or-apply-for-a-licence/)Environmental Protection Agency, checked 3 November 2026. The 25 and 2,000 cubic metre a day water abstraction thresholds.
3. [Current EIA screening thresholds (Schedule 5, Part 2)](https://consult.housing.gov.ie/en/system/files/materials/8/Current%20Environmental%20Impact%20Assessment%20Screening%20Thresholds.pdf)Department of Housing, Local Government and Heritage, checked 3 November 2026. The project sizes above which an EIA report is mandatory.
4. [About trade effluent](https://water.ie/business/trade-effluent/about)Uisce Éireann, checked 3 November 2026. Who needs a trade effluent licence to discharge to the public sewer.
5. [Discharge licences](https://www.dublincity.ie/environment-and-climate-action/protecting-against-water-pollution/discharge-licences)Dublin City Council, checked 3 November 2026. Section 4 licences for discharges to waters and Section 16 licences for discharges to sewer.
6. [Air Dispersion Modelling Guidance Note (AG4)](https://www.epa.ie/publications/compliance--enforcement/air/air-guidance-notes/epa-air-dispersion-modelling-guidance-note-ag4-2020.php)Environmental Protection Agency, 2020. How licensed sites model the spread of air emissions.
7. [Guidance Note for Noise: licence applications, surveys and assessments (NG4)](https://www.epa.ie/publications/monitoring--assessment/noise/guidance-note-for-noise-licence-applications-surveys-and-assessments-in-relation-to-scheduled-activities-ng4.php)Environmental Protection Agency, 2016. The noise survey and assessment method for licensed sites.
8. [Contact us](https://fisheriesireland.ie/contact-us)Inland Fisheries Ireland, checked 3 November 2026. The 24-hour line for pollution and dead or distressed fish in inland waters.

## Tell us about the campus

### What we ask for

- The site location and boundary
- The planning stage you are at
- The building, generator and fuel storage layout
- Expected water use and where water will be discharged
- The planning conditions you need to meet, if any

### Reply

Within one working day.

For a spill or pollution incident, phone [0818 714 002](tel:0818714002) at any hour. The duty engineer confirms the response on the call.

[Send your campus enquiry](https://verde.ie/contact?sector=data-centres)

[Call 0818 714 002](tel:0818714002)

Office [01 201 1260](tel:+35312011260) or [info@verde.ie](mailto:info@verde.ie)

## Related pages

- [Hydrogeology and groundwater](https://verde.ie/services/water-hydrogeology): Abstraction thresholds, yield testing and dossiers.
- [Construction dewatering](https://verde.ie/services/construction-dewatering): Design, licensing and monitoring of dewatering.
- [Air, noise and acoustics](https://verde.ie/services/air-noise-acoustics): Generator noise and emissions to EPA guidance.
- [EPA and IPC licensing](https://verde.ie/services/ippc-waste-licensing): Which authorisation applies, and the application steps.
- [Appropriate assessments](https://verde.ie/services/appropriate-assessments): Screening and Natura Impact Statements.
- [Energy & Electricity Infrastructure](https://verde.ie/sectors/energy-and-electricity): Planning and monitoring for grid projects.