# Construction Dewatering – Meta HQ, Dublin

Dewatering in clay and bedrock for a 14m treble-basement dig on a 10,000m² Dublin 4 site, with pH control and over 200 tonnes of sludge removed.

![Construction Dewatering – Meta HQ, Dublin](/__l5e/assets-v1/624f486c-1078-4e83-90cc-8da873691ef8/construction-dewatering-meta-dublin.jpg)

Project narrative

Construction dewatering at landmark site, Fibonacci Square, Ballsbridge, Dublin 4. Redevelopment of the former AIB Bank centre to the state-of-the-art, 2nd largest Meta (Facebook) campus in the world.

Dewatering system installation with pH and sediment control

Sump dewatering in clay and bedrock strata

Active recharging to ground and combined sewer

Extensive flocculent application and sludge management >200 tonnes sludge removal.

Verde provided construction dewatering services for John Sisk & Son a Fibonacci Square, Dublin, the new Meta HQ. The site was across 10,000m2 and involved a 14 metre dig with seccant wall construction to facilitate the installation of a treble basement.

Verde installed a bespoke dewatering system to control waters in clay and bedrock strata. High levels of sediment were extracted during the dewatering process and high levels of pH were controlled prior to discharge and recharge.

Delivered under

- [Construction dewatering](https://verde.ie/services/construction-dewatering)

Discuss a similar project

[Start a conversation](https://verde.ie/contact)

Keep reading

## Related case studies

[All 22 case studies](https://verde.ie/projects#case-studies)

[Construction Dewatering Construction Dewatering – Profile Park, Dublin Water control for the first two phases of a 22-acre, 52MW data centre campus at Profile Park, Dublin, from licensing to compliance monitoring.](https://verde.ie/projects/construction-dewatering-profile-park)

[Construction Dewatering Construction Dewatering – 137–140 Abbey Street Upper, Dublin 1 Dewatering management, regulatory compliance and environmental monitoring for construction works in an urban setting at 137–140 Abbey Street Upper, Dublin 1.](https://verde.ie/projects/construction-dewatering-137-140-abbey-street-upper-dublin-1)

[Construction Dewatering Construction Dewatering – Ballymore Craddockstown Developments Limited, Kildare Ongoing construction dewatering with trade effluent treatment for pH and suspended solids on works at Tipper West, Naas, Co. Kildare. Verdé case study, 2025.](https://verde.ie/projects/construction-dewatering-ballymore-craddockstown-developments-limited-kildare)