Construction Dewatering · Case study
Construction Dewatering – Ballymore Craddockstown Developments Limited, Kildare
Ongoing construction dewatering with trade effluent treatment for pH and suspended solids on works at Tipper West, Naas, Co. Kildare. Verdé case study, 2025.

Project narrative
Construction Dewatering @ Ballymore Craddockstown Developments Limited.
Verdé is proud to continue supporting Ballymore Craddockstown Developments Limited in the ongoing works at Tipper West, Naas, Co. Kildare . This collaborative project highlights our dedication to environmentally responsible site services and long-term client partnerships.
Trade effluent treatment (pH and suspended solids)
Dewatering - Ballymore Craddockstown Developments Limited
Verde Environmental Consultants is proud to continue supporting Ballymore Craddockstown Developments Limited in the ongoing works at Tipper West, Naas, Co. Kildare . This collaborative project highlights our dedication to environmentally responsible site services and long-term client partnerships.
Ballymore Craddockstown Developments Limited
Keep reading
Related case studies
Construction Dewatering
Construction Dewatering – Profile Park, Dublin
Water control for the first two phases of a 22-acre, 52MW data centre campus at Profile Park, Dublin, from licensing to compliance monitoring.
Construction Dewatering
Construction Dewatering – 137–140 Abbey Street Upper, Dublin 1
Dewatering management, regulatory compliance and environmental monitoring for construction works in an urban setting at 137–140 Abbey Street Upper, Dublin 1.
Construction Dewatering
Construction Dewatering – Garda Ops Centre
Deep-well dewatering for a 10m dig on a 7,000m² Dublin 8 site, discharging about 3,000m³ a day under licence to the River Camac for 11 months.