Verde Environmental Consultants & Oil Leak Clean Up Specialists Supreme court dismisses Apple data centre Environmental Impact Assessment case appeal – Verde – Complete Environmental Solutions
/ blog / Supreme court dismisses Apple data centre Environmental Impact Assessment case appeal

Supreme court dismisses Apple data centre Environmental Impact Assessment case appeal

Fitzpatrick and Daly v An Bord Pleanála, Apple Distribution International, and the Minister for Housing, Planning and Local Government and the Attorney General [SC Appeal No. 157/2017]

On 11th April 2019, the Supreme Court decided to dismiss the appeal in the Apple data centre case. The Appellants had argued in the High Court and the Supreme Court that An Bord Pleanála (the Irish Planning Board) had failed to carry out an Environmental Impact Assessment (‘EIA’) of the proposed data centre development in accordance with the EIA Directive 2011/92/EU.

The Board’s EIA process was upheld by the High Court in a judgment delivered in October 2017, following a hearing in March 2017.  In April 2018 the Supreme Court decided to allow the appeal to be made. The hearing of that appeal took place at a special sitting of the Supreme Court in Galway on 6 March 2019.

The proposed data centre development comprised an application for permission for one data centre hall and a separate application for permission for a large electricity substation and associated grid connection development. The application was accompanied by an Environmental Impact Statement for the purposes of carrying out an EIA, and a ‘masterplan’ indicating that there may be future phases of development at the site of up to a maximum of eight data centre halls. Each additional data centre hall would require a further planning application to be made, and each application would be subject to further EIA.

The appeal centred on whether the Board was obliged as a matter of law to carry out an EIA of the entire masterplan of eight data centre halls and the substation development. In the alternative, it was argued that the Board was obliged, in the EIA of the single data centre hall, to also assess the likely environmental impacts arising from future phases of development as far as practically possible and that in this case the Board did not do so.

The Supreme Court upheld the High Court judgment and the Board’s approach to EIA. The Court held that:

  1. The Board was not obliged to carry out EIA of the entire masterplan before deciding on the applications for the data centre hall and substation.
  2. The Board was only obliged to carry out an EIA of the proposed developments for which planning permission was sought.
  3. The Board was additionally obliged to take account as far as practically possible of the environmental effects of potential later phases of development identified in the masterplan.
  4. The Supreme Court was satisfied that the Board had met its legal obligations in full, accordingly the appeal was dismissed

The Appellants had urged the Supreme Court to make a reference to the Courts of Justice of the European Union (CJEU) for a clarification of what is required in these circumstances. The Court held that it was not necessary to make any reference to the CJEU, as the obligations under the EIA Directive are clear.

The Court was satisfied that there was no ‘project splitting’ to avoid the full rigours of EIA, nor was there a failure to carry out a cumulative impact assessment of the data centre hall with the proposed substation and grid connection development.

The Court was satisfied that each data centre hall development is ‘stand-alone’ in the sense that they are not functionally or legally interdependent. Each is subject to a requirement for planning permission, and each new development would be subject to EIA which would need to be both backward and forward looking, taking into account as far as practically possible, of future environmental impacts. It is possible that any one of those applications may be subject to refusal if it is considered that the environmental impacts are unacceptable. Therefore, whilst the first phase of development undoubtedly gives the developer a ‘foot in the door’ for future phases, the approval of such future phases will be subject to separate planning decisions and EIA.

This Judgment does not create any new law, but usefully confirms that the approach taken by the Board and planning authorities to date in similar multi-stage developments, such as road and rail projects, and housing and regeneration schemes, is correct and in accordance with EU law.

Source – Lexology: Alice Whittaker, Philip Lee

Verde Environmental Consultants in-house expertise in the main Environmental Impact Assessment (EIA) disciplines and strategic partnerships enables us to efficiently project manage the EIA process, including:

  • Initial screening
  • Scoping
  • Alternatives evaluations
  • EIA / EIS preparation
  • Presentation at public enquiry

Related Blog Posts

Environmental licenses required for Irish data centres

Environmental issues for Irish data centres

Dublin mountain visitor centre on hold over environmental assessments

Noise fear as Amazon plans £267m Dublin data hub

Related Projects

Top